Which of the following is not an input to the cost control process?
A. Performance measurement
B. Cost baseline
C. Performance reports
D. Change requests
ANS: A
Which of the following is not a tool or technique for cost control?
A. Cost change control system
B. Revised cost estimates
C. Performance measurement
D. Additional planning
ANS: B
Which of the following is not an output of the cost control process?
A. Revised cost estimates
B. Budget updates
C. Workarounds
D. Estimate at completion
ANS: c
As project manager, which of the following activities most deserves your
immediate attention?
A. ACWP = $3,000 and BCWP = $2,900
B. BCWS = $3,000 and BCWP = $2,900
C. ACWP = $3,000 and BCWP = $3,200
D. BCWP = $3,000 and ACWP = $2,400
ANS: D |
|